Runway 2/20 Pavement Maintenance
Summer 2020 Runway 2/20 maintenance work will consist of crack sealing, a seal-coat application and new pavement markings. Runway 2/20 is 6,526' x 150'.
Runway 2/20 Closure
- Nightly from 10:15 PM - 6:30 AM
- Monday, August 3 through Thursday, August 10 (may be completed sooner!)
Rotor Operations ONLY
- North apron (by FBO & Fuel Island) to remain open during runway closure
Construction Access & Staging Area
- Link to Construction Safety & Phasing Plan
- Purple hightlighted area of the apron for rotor ops during rwy closure
- Staging area is at Lear Gate
- Construction lane identified with lit barricades from Lear Gate to work area
Effected NAVAIDS
- Localizer (FAA to turn off for duration of project)
- Glide Slope (FAA to turn off for duration of project)
- MALSR (FAA MAY keep on)
- VOR (FAA to keep on - informational ticket)
- PAPI's (Will remain on)
Effected Procedures
- ILS (Not available)
- RNAV/GPS (Available)
- VOR (Available)
CONSTRUCTION TEAM
Engineering: Mead & Hunt Engineering
Contractor: Maxwell Construction
NAVAIDS: FAA Columbia Basin SSC
Financial Partners: FAA, WSDOT Aviation and Port of Walla Walla
BUDGET
Total = $483,319.00
- FAA Share (91.88%) = $444,073.00
- WSDOT Share (3.6%)= $17,497.00
- Port Share (4.52%) = $21,749.00